Jobs, constraints, objective and priorities.
Implemented hereSeven jobs. Four shifts. One inspectable route from workload to decision.
A, E and G are always mandatory. Survey A precedes intervention B; survey C precedes intervention D.
Jobs, constraints, objective and priorities.
Implemented hereExact schedule, feasibility check and auditable response.
Implemented hereQualified encoding, dispatch and checked execution.
Interface contractThis module does not run FQKL, ERDA or QuantumTwin models. It creates a concrete workload interface for their future integration. No QPU execution, operator deployment or quantum advantage is claimed.
Every job lasts one abstract shift and consumes one interchangeable capacity slot. The labels illustrate an industrial problem; this is not an operational drilling model. Real systems need durations, travel, rig compatibility, uncertainty, safety rules and qualified data.
| Job | Base points | Due shift | Latest | Required | Predecessor |
|---|
The objective sums base points × energy-priority weight, minus 3 points per shift after the due shift. Release is shift 1 for all jobs. Deferred jobs earn zero. Late jobs may still be feasible before their latest shift. “Optimal” means the best feasible assignment for this declared finite model. Ties prefer more completed jobs, then earliest lexicographic A–G assignment.